The AI Power Chain series · Part 1 of 15

Glossary of terms used

AEP
American Electric Power. Investor-owned utility operating in 11 US states including Ohio.
CAISO
California Independent System Operator. The grid operator for most of California.
ERCOT
Electric Reliability Council of Texas. Grid operator for most of Texas, operating largely as an electrical island.
EV
Enterprise Value. Purchase price plus debt assumed minus cash. Total value of the business excluding capital structure.
GW
Gigawatt. One thousand megawatts of electrical power.
GaN
Gallium Nitride. Wide-bandgap semiconductor material used in RF and power applications.
MISO
Midcontinent Independent System Operator. Regional grid operator covering 15 US states and Manitoba.
MV
Medium Voltage. Typically 1 kV to 35 kV. The voltage class connecting data centre power distribution to the utility grid.
MVA
Mega-Volt Amperes. Apparent power rating unit used for transformers and switchgear.
MW
Megawatt. Unit of electrical power. A large modern data centre draws tens to hundreds of MW.
PJM
PJM Interconnection LLC. Regional grid operator covering 13 US states plus DC. Includes Ohio, where the NVIDIA/OpenAI campus lands.
SMR
Small Modular Reactor. Nuclear reactor design with output typically below 300 MWe, envisioned for co-located generation.
SiC
Silicon Carbide. Wide-bandgap semiconductor material used in high-voltage power electronics.
TAM
Total Addressable Market. The maximum revenue opportunity available if a product served every potential customer segment.
ADI KUMAR · POWER & DIGITAL INFRASTRUCTUREAUGUST 2026 · V1 · ~45 MIN READ
The AI Power Chain · Part IV of VI
Market deep dive · Grid interconnect & interconnect equipment

The Interconnect Stack: Transformers, Switchgear and the Grid Equipment That Gates the AI Buildout

Every gigawatt of AI capex assumes an interconnected grid connection with sufficient MV switchgear, a large power transformer and a set of medium-voltage cables to route the current. In 2026 that assumption no longer holds. LPT lead times have doubled since 2023, GOES supply is concentrated in three producers, US interconnect queues run four years, and hyperscalers have started building their own generation to escape the wait. A layer-by-layer analysis from grain-oriented electrical steel to grid queue reform.

Executive summary. Nine findings.
  1. Grid interconnect has become the binding constraint on AI, ahead of compute, cooling, and chip supply. New large-load interconnect timelines in PJM, ERCOT, MISO and CAISO commonly run 4-7 years from application to energisation. Every hyperscaler ordering GW-class capacity in 2026 is planning around a wait that could stretch into the next decade.
  2. Large power transformer lead times have doubled since 2023. A 138/33 kV or 230/34.5 kV substation-class LPT that took 50-60 weeks pre-pandemic now takes 120-150+ weeks in North America. Global order books at Hitachi Energy, Siemens Energy and GE Vernova have been reported past record highs, with the three sitting on multi-year backlogs.
  3. GOES (grain-oriented electrical steel) is the underlying materials chokepoint. Roughly five producers globally (JFE Steel, Nippon Steel, POSCO's spinoff, ArcelorMittal / Cogent, NLMK), with China's Baosteel and TISCO adding capacity. GOES is the transformer core material and its manufacturing takes 12-18 months to expand. It is the Kuraray of the interconnect stack.
  4. Behind-the-meter power has moved from workaround to strategy. Amazon at Susquehanna, Meta at Clinton (Constellation), Microsoft at Three Mile Island, Google's Kairos SMR MOU, plus dozens of gas-turbine and Bloom Energy fuel cell deals. What used to be "on-site generation for redundancy" is now "on-site generation because we cannot wait for the grid".
  5. Copper demand from AI adds a materials layer stress that most models miss. Hyperscale racks use roughly 3-5× the copper per MW of a legacy enterprise data centre. On top of EV and renewables demand, AI could add 1-2 million tonnes/year of incremental copper consumption by 2030, into a supply base already forecasting deficits.
  6. The M&A window for interconnect assets has closed. Hitachi bought ABB Power Grids in 2020. GE broke out Vernova in 2024. Cameron International, Emerson process, PGE, Sensata: the big consolidations are done. What remains is bolt-ons and JVs.
  7. Digital and asset-managed transformers are the emerging profit lever. Adding sensor packages, oil-quality monitoring and thermal telemetry lets OEMs sell a service tail alongside the box. Hitachi Energy, Siemens Energy and Mitsubishi Electric all now have dedicated digital-transformer product lines. Software attach is small revenue today, high-margin, and structurally growing.
  8. Chinese equipment is qualifying into the AI supply chain for cables and medium-voltage switchgear, less so for large power transformers. TBEA and Baoding Tianwei have made international sales, but hyperscalers' provenance rules and utility qualification cycles are the real barriers.
  9. Bottom-up TAM. AI data centre interconnect capex is at roughly $12-18B in 2026 (~$150-200k per MW of IT load, on ~8GW of new build) rising to $45-65B by 2030 as the buildout scales. Transformers, switchgear and cables dominate; behind-the-meter generation is the emerging category.
GWStage 0 · The thesis
The AI Power Chain · six essays, one physical arc

The series walks a single physical path. It begins at the medium-voltage utility bus at the site fence, steps down through the substation and switchgear, arrives at the datacenter rack where 800V DC is stabilised by the capacitor stack, is converted by silicon-carbide switches to 48V, is distributed across the rack by copper busbars and whips, is stepped down again by multi-phase controllers on the accelerator board to 0.8V, and finally routed through the on-package power delivery network to a transistor gate drawing over 2,000 amperesWaste heat from every conversion stage is removed by the thermal stack. The whole thing is packaged inside a factory-modular building because there aren't enough electricians to build it stick-frame. Six essays. One 800V → 0.8V staircase.

  1. Part I. The Capacitor Stack 800VDC at the rack
  2. Part II. The Wide-Bandgap Stack SiC and GaN conversion
  3. Part III. The Thermal Stack Removing the waste heat
  4. Part IV. The Interconnect Stack Busbars and whips (you are here)
  5. Part V. The On-Package Delivery Stack 48V to 0.8V
  6. Part VI. The Modular Datacenter Stack How the building gets built
$150k+
Estimated interconnect capex per MW of AI IT load, 2026 base
~3-5×
Copper per MW in a hyperscale AI rack vs a legacy enterprise data centre
Interconnect lead time expansion, by equipment class
Reported delivery lead times, weeks, 2019 vs 2026, indicative
Compiled from vendor guidance, EPRI briefings, DOE Loan Programs Office reports, and utility engineering-firm surveys through mid-2026. Ranges are wide because lead time depends on capacity class, voltage, customer priority and manufacturer relationship. The direction and magnitude of the change are consistent across sources.

The mismatch between AI capex velocity and interconnect physics has driven the behind-the-meter generation wave, the acceleration of small modular reactor pilots, hyperscaler direct multi-year procurement contracts with transformer OEMs, and a redrawing of the map of where data centres can be built. The utility-equipment supply chain, which had been low-growth and stable for two decades, is now one of the two or three most strategically constrained resources in AI infrastructure.

MAPThe framework · Eight layers, one grid path

The interconnect value chain, layer by layer

The capacitor stack divided by timescale. The wide-bandgap stack divided by process step. The thermal stack divided by heat-path position. The interconnect stack divides by voltage class and physical position between utility and rackEach layer has a different competitive structure, a different concentration profile, and a different lead-time exposure. The market map below names the players at every layer. Two things stand out before reading it: the Japanese and Korean depth in materials and heavy equipment (GOES, LPT, HV cables) and the fact that the same four or five industrial groups (Hitachi Energy, Siemens Energy, Schneider Electric, ABB, Eaton) appear at multiple layers. Interconnect is a heavily integrated business, and it has been that way for decades.

The AI data centre interconnect market map
Named players by layer, leaders highlighted, and August 2026
L1Grain-oriented electrical steel (GOES)Silicon-steel laminations for transformer cores · roughly 5 global producers
Cogent (Tata) UK/IN
ArcelorMittal FR
POSCO KR
NLMK / DK RU/DK
Baosteel CN
TISCO / Taiyuan CN
AK Steel (Cleveland-Cliffs) US
Wuhan Iron & Steel CN
Steel Authority of India IN
L2Large power transformers (LPT)≥100 MVA units for substations · concentrated in three global majors + regional players
Hitachi Energy (ex-ABB) CH/JP
Siemens Energy DE
GE Vernova US
Hyundai Electric KR
HHI (LS Group) KR
Toshiba Energy Systems JP
WEG BR
Prolec-GE (Xignux) MX
SGB-SMIT DE
TBEA CN
Baoding Tianwei CN
Wanshiba (WEG-China) CN
CG Power / Bharat Heavy IN
Delta Star US
Virginia Transformer US
ERMCO / Pennsylvania Transformer US
L3MV / LV switchgearAir-insulated, gas-insulated (SF6), vacuum, dry-air · switchgear for substation and distribution
Schneider Electric FR
ABB CH
Eaton US/IE
Siemens DE
Hitachi Energy CH/JP
Powell Industries US
Legrand (industrial) FR
Alstom Grid (ex-GE) FR
LS Electric KR
Hyundai Electric KR
CHINT · Delixi CN
nVent (Erico / Hoffman) US/IE
Vertiv (integrated) US
Rittal DE
L4MV / HV cablesXLPE-insulated MV cables, often kilometres per campus, and four global majors + Chinese/Korean scale
Prysmian IT
Nexans FR
NKT DK
LS Cable & System KR
Southwire US
General Cable (Prysmian) US
Hengtong Group CN
ZTT (Jiangsu Zhongtian) CN
Far East Cable CN
Elka (Cable Coop) PL
L5Copper & conductor materialsMine, smelter, and rod & wire · fabricated busbar
Freeport-McMoRan US
Southern Copper (Grupo México) PE/MX
BHP · Rio Tinto AU/UK
Glencore CH
Codelco CL · state
Zijin Mining CN
Aurubis DE · smelter
KME IT/DE · fab
Wieland Group DE · fab
Southwire US · fab
Sterlite / Vedanta IN
L6Backup generation · gensetsDiesel and natural-gas standby, years-long lead times, and integrated with fuel and controls
Caterpillar US
Cummins US
Rolls-Royce mtu DE/UK
Kohler US
Generac US · industrial
MAN Energy Solutions DE
Vertiv (Liebert) US · integration
Eaton (Cyclonaire/Fibrebond) US · packaging
L7Behind-the-meter powerGas turbines, fuel cells, and SMR (emerging) · alternative sources when grid queues bite
Bloom Energy US · SOFC
GE Vernova (LM6000/LM2500) US · gas turbine
Solar Turbines (Caterpillar) US
Siemens Energy (SGT) DE
FuelCell Energy US · MCFC
SFC Energy DE
NuScale US · SMR
X-Energy US · SMR
Kairos Power US · SMR
Oklo US · SMR
GE Hitachi (BWRX-300) US/JP · SMR
Rolls-Royce SMR UK
L8Grid connection · regulated utilityNot a commercial market · the constraint everything else is trying to route around
PJM Interconnection US · MW East
ERCOT US · Texas
MISO US · Midwest
CAISO US · California
ENTSO-E TSOs EU
National Grid (UK ESO) UK
TenneT · 50Hertz DE
Dominion · AEP · Duke US utilities
PG&E · SCE US · CA
Berkshire Hathaway Energy US
United StatesEuropeJapanChinaKoreaIndiaShaded tiles = category leaders
Reading this map. The shares and lead times quoted throughout this piece are approximate and drawn from public research of differing vintages and scopes. Treat them as positional. Two features stand out. First, the same handful of Western industrials appear at three or more layers each: Hitachi Energy, Siemens Energy, GE Vernova, Schneider Electric, Eaton, ABB, Mitsubishi Electric. Vertical integration across the transformer / switchgear / cable path is the norm, and it has been for decades. Second, the geography of concentration matters: large power transformers are majority Asian-manufactured (Japanese, Korean, plus rising Chinese and Indian), GOES is majority Japanese, and MV cables are split between three European giants and AsiaThe North American production base is thin and expanding slowly.
L1Grain-oriented electrical steel
In brief

Grid interconnect is now the binding constraint on AI data centre buildout. Transformer lead times exceeded 200 weeks in 2025-26 per industry disclosures. Hyperscaler substation queue slots are held years in advance. The vendor stack (Eaton, Vertiv, ABB, Schneider, Prysmian) is consolidating rapidly. Eaton alone has closed Fibrebond ($1.4B, April 2025), Ultra PCS ($1.55B, January 2026) and Boyd Thermal ($9.5B, closed March 2026) per company press releases.

The material chokepoint most models don't see

A transformer core moves past a solid iron block. If it were, eddy currents circulating in the metal during AC cycles would dissipate the transformer's rated power as heat within minutes. Cores are built from thin laminations of silicon-alloyed iron in which the crystal grains have been oriented along the direction of magnetic flux. This "grain orientation" is achieved through a specific rolling, annealing and coating process that took decades to develop and is dominated globally by roughly five producers. The resulting material (grain-oriented electrical steel, or GOES) has an order-of-magnitude lower core loss than random-orientation steel, which is what makes practical 100-MVA-and-larger transformers possible at 99%+ efficiency.

GOES production is capital-intensive and slow to scale. A greenfield GOES line takes 3-5 years to design, permit and commission, and roughly 12-24 months to reach qualified output at commercial defect densities. Since the shale-gas and renewables buildout began in the early 2010s, GOES has cycled between periodic shortage and glut. Since 2022 the balance has been squarely on the shortage side, driven by simultaneous demand from grid expansion, renewables integration, EV charging infrastructure and now hyperscale data centres.

GOES supply by producer, indicative
Approximate global GOES production share, 2025 basis. Directional.
Combined estimates from industry press (Metal Bulletin, SteelOrbis), corporate disclosures and trade press through 2025. Chinese production has grown fastest but is largely consumed domestically. Japanese, Korean and European material dominates the export market that supplies Western LPT builders.

The three grades that matter

GOES splits into three commercial grades: conventional (CGO), high-permeability (HGO or Hi-B), and domain-refinedEach represents a step up in magnetic performance and a corresponding step up in price. Modern high-efficiency transformer designs use HGO or domain-refined material for the core; the very highest-tier designs (railway traction, HVDC valve transformers, hyperscale substation LPT) use domain-refined material with laser-scribing to further reduce core loss. Nippon Steel and JFE dominate the domain-refined grade; Cogent and POSCO offer competitive alternatives at slight cost disadvantage.

The AI-relevant point is that the hyperscale substation transformer lands squarely in the segment where domain-refined GOES matters most. It is the segment where the supply base is most concentrated, where lead times have expanded most, and where price has moved most. This is the "materials layer" chokepoint of the interconnect stack, and it plays the same role that Kuraray's cathode carbon plays in the capacitor essay or Japanese silicon nitride plays in the wide-bandgap essay: small revenue, operating leverage, extreme concentration.

The amorphous metal alternative. Amorphous-metal transformer cores (using Metglas from Hitachi Metals / Proterial, or equivalent products from Advanced Technology & Materials in China) achieve 70-80% lower no-load losses than GOES. They have been commercial since the 1980s for distribution transformers. The reason they have not displaced GOES in large power transformers is that amorphous ribbon is thinner, harder to work, and mechanically fragile compared to grain-oriented laminations. Handling adds cost. As efficiency regulations tighten (EU EcoDesign 2021, US DOE 2024 updates) amorphous is gaining share at the small end. In LPT-scale devices it remains niche, but a supply squeeze on GOES could accelerate qualification.
L2Large power transformers

What is the 200-tonne transformer bottleneck?

The large power transformer is the piece of equipment that steps utility voltage down to something a data centre can use. A hyperscale campus typically has multiple 50-150 MVA units in its main substation, plus smaller distribution transformers throughout. A single LPT weighs 100-400+ tonnes, ships by rail or specialised truck, and is oil-filled, so site delivery and installation is a construction project in itself. Each unit is essentially bespoke: designed to the utility's voltage class, the site's short-circuit rating, the loading profile and the environmental constraints. There is no mass-market SKU.

The market structure and where the concentration is placed

Three companies (Hitachi Energy, Siemens Energy, GE Vernova) hold the majority of the global market for large power transformers over 100 MVA. Hitachi Energy inherited ABB's power grids business in a 2020 acquisition and has become the largest single player, with reported multi-year backlogs. Siemens Energy carved out from Siemens AG in 2020 and is the closest Western competitor. GE Vernova spun out of General Electric in 2024 as the dedicated energy business. Mitsubishi Electric and Hyundai Electric round out the top five with strong Asian franchises. Below them, a long tail of regional and specialist producers (WEG, Prolec, SGB-SMIT, Delta Star, Virginia Transformer) serve smaller units and regional markets.

US production capacity is thin and expanding slowly. Prolec-GE, Virginia Transformer, Delta Star, Pennsylvania Transformer and a handful of smaller manufacturers make up the domestic base, which was estimated in the DOE's 2023 supply-chain review at roughly 20% of US LPT demand at typical utility replacement rates. That share is now unable to keep pace with hyperscale-driven demand. Multiple capacity expansions have been announced (Prolec in Monterrey, Hitachi in South Boston Virginia, HHI in Alabama), but a new LPT plant takes 3-5 years to build and qualify. None of the announcements will substantially relieve US supply before 2028.

Global LPT market share by manufacturer
Approximate revenue share, ≥100 MVA units, 2024-25 basis
Compiled from Metal Bulletin, T&D World, corporate disclosures. Three global majors + two strong Asian franchises hold roughly 65% of the market; the remainder is fragmented across regional players. Share of new orders in 2025-26 skews further toward the top three, which is the mechanism behind their lengthening backlogs.

The lead time story, in detail

Pre-pandemic, an LPT for a US utility was a 40-60 week engagement. Order placed, engineering complete in ~10 weeks, GOES procured and processed into laminations, core stacked, windings wound, tank assembled, oil-filled, factory tested, shipped. In 2026 that same engagement is quoted at 120-150 weeks by most Western OEMs, with some hyperscale-scale units pushing 200 weeks. Three factors drove the expansion, in roughly the order that counts.

First, demand doubledUtility grid modernisation (regulated capex), renewables interconnection (each wind or solar project needs a step-up transformer), EV charging build-out, industrial reshoring, and now AI data centres have all been ordering LPTs simultaneously, at rates the manufacturing base was never sized for. Global LPT demand has been reported to have doubled between 2020 and 2025.

Second, the supply base did not expand in stepTwo decades of low-single-digit utility spending growth had left OEMs with lean production footprints. Adding a new manufacturing bay costs $100M+ and takes 3-5 years. Announced capacity expansions have been substantial (Hitachi Energy alone has announced roughly €4.5B of grid-equipment capex through 2027) but the ramp curves lag demand by 2-3 years minimum.

Third, materials tightenedGOES supply, described above, is the immediate constraint at the material layer. Transformer oil (mineral or ester), copper wire, insulation paper (kraft pressboard), and specialty bushings have all seen extended lead times through 2024-25. Each is a smaller constraint than GOES but the compounding effect holds.

Hitachi Energy order backlog trajectory
Reported order book / revenue ratio, indicative
Hitachi Energy has publicly reported order backlogs that have tripled since 2020 to record levels by 2025. The ratio of backlog to revenue is the operationally significant number: at 2-3× annual revenue, a company has visibility on multi-year growth but cannot flex quickly. Siemens Energy and GE Vernova report similar patterns.
L3MV / LV switchgear

The equipment that routes and protects

Switchgear is the equipment that connects and disconnects circuits under load, isolates faults, and protects downstream equipment from short circuits. A hyperscale campus has switchgear at every voltage class: MV switchgear (typically 5-38 kV) in the substation and at row-level distribution, LV switchgear (below 1 kV) at the panel-board level. Different physics govern each: MV switchgear must interrupt current at kV levels without sustaining an arc, which is what drives the choice of insulation medium.

MV switchgear insulation media compared
Radar comparison across five criteria: interrupting capacity, environmental profile, footprint, cost, service maturity
Air-insulated (AIS) is the incumbent, well understood, largest footprint. SF6-insulated (GIS) has the smallest footprint but the highest global-warming potential (GWP ~23,500). Vacuum interrupters are increasingly standard for MV breakers. Dry-air / fluoro-nitrile alternatives are emerging as SF6 phase-out accelerates under EU F-gas regulation and analogous US EPA rules.

The SF6 phase-out

Sulphur hexafluoride (SF6) has been the standard insulation gas for high-voltage switchgear since the 1970s. It has excellent dielectric strength (per unit volume, roughly 3× that of air), good arc-quenching properties, and long service life. It is also the most potent greenhouse gas ever regulated, with a GWP roughly 23,500× that of CO₂ and an atmospheric lifetime of 3,200 years. Under the EU F-gas Regulation revised in 2024, SF6 will be prohibited in new MV switchgear from 2028-2030 depending on class, with HV following. US EPA and Californian rules are moving in the same direction.

The industry response has been alternative insulation gases (Hitachi Energy's EconiQ using C4-fluoronitrile, Siemens' Blue GIS using clean air, GE's g3 using C5-fluoroketone) and vacuum interrupters for medium-voltage classes. The alternatives are more expensive, some bring residual environmental concerns (fluoroketones degrade to PFAS in the atmosphere), and each requires qualification against long-established SF6 designs. Data centre operators specifying substations in 2026 face a real design choice between staying with SF6 for immediate delivery and paying a premium for clean-gas alternatives that align with corporate sustainability commitments.

L4MV cables

Kilometres of XLPE per campus

A hyperscale data centre campus typically comprises 5-15 buildings on a site of a few hundred hectares, connected by underground medium-voltage cable runs. The main substation feeds distribution transformers scattered near the buildings, and the distribution transformers feed the racks. Total MV cable per site can run into the tens of kilometres. Every kilometre is engineered for the voltage class (typically 15-35 kV), fault-current rating, ampacity and burial depth.

The dominant cable technology is cross-linked polyethylene (XLPE) insulated cable with a copper or aluminium conductor. XLPE is thermoset (cross-linked during curing so it does not melt at operating temperature), which lets it handle higher continuous current than earlier PVC-insulated designs. Copper conductors are used where ampacity per cross-section matters most; aluminium is used where cost dominates and larger cross-sections are acceptable.

Global MV cable capacity concentrates in three European majors (Prysmian, Nexans, NKT), two Asian franchises (Sumitomo Electric, LS Cable & System), and a rising Chinese cohort (Hengtong, ZTT, Far East Cable). Similar to LPT, capacity expansion is slow: a new XLPE extrusion line takes 2-3 years to qualify. Prysmian and Nexans have both announced major capex programmes for MV and HV cable capacity through 2027, driven by offshore wind, HVDC interconnectors, and data centre demand.

Why aluminium doesn't fully substitute for copper. Aluminium is roughly a third of copper's mass per unit volume, cheaper per tonne, and has adequate conductivity for many applications. In data centre MV cables it is used routinely for the largest cross-sections. But aluminium has three tradeoffs: it is 60% as conductive per unit cross-section as copper (so an aluminium cable of the same ampacity is physically larger), it work-hardens over thermal cycles at connection points (which is why terminations use specialised techniques), and it cannot be used where mechanical flexibility is paramount. For rack-scale wiring, busbars and switchgear internal connections, copper remains dominant. Aluminium substitution holds but bounded.
L5Copper

The commodity underneath everything

Copper is the material that binds the interconnect stack together. Every transformer winding, every busbar, every MV cable, every rack-scale power distribution unit uses copper as the conductor of choice. A hyperscale AI data centre uses roughly 30-50 tonnes of copper per MW of IT load, according to widely cited industry estimates from 2024-25, which is 3-5× the copper intensity of a legacy enterprise data centre. The multiplier comes from higher rack currents (800VDC at ~750A per rack), denser distribution, more redundancy, and higher-ampacity bus systems.

Copper demand from AI data centres in context
Estimated incremental copper demand by end market, million tonnes/year by 2030
Compiled from BHP, Wood Mackenzie, S&P Global Commodity Insights and IEA outlooks through 2025. AI data centres add roughly 1-2 Mtpa of incremental copper demand by 2030 on top of the much larger EV and renewables buildout demand. Cumulative copper deficit forecasts through 2030 range from 6-10 Mtpa without new mine investment.

Global copper mine production is roughly 22 Mtpa (2024). Adding EV, renewables, grid modernisation and AI data centre demand together, most credible forecasts point to a sustained deficit through the 2030s absent significant new mine investment. Mine development takes 10-20 years from discovery to first production, and the most attractive undeveloped ore bodies (Chile, Peru, DRC, Mongolia) are increasingly complicated by permitting, community consent and geopolitical risk. Copper is unlikely to run out (recycling handles roughly a third of current supply), but the price signal from the deficit is likely to be substantial, and it will show up in every layer of the interconnect stack.

L6Backup generation

The generators that used to be an afterthought

Every data centre has backup generation. It used to be a routine specification: rated for eight to twelve hours of runtime on onboard diesel, sized for full load, arranged in an N+1 or 2N redundancy configuration, exercised monthly, and forgotten about the rest of the time. In 2026, backup generation is a strategic variable. Diesel gensets have lead times running past two years for the largest units. Natural-gas gensets, favoured for lower emissions and lower fuel storage requirements, run longer. Behind-the-meter gas turbines (below) increasingly displace both.

The three largest genset manufacturers globally are Caterpillar, Cummins and Rolls-Royce mtu in the diesel/gas engine class. Mitsubishi Heavy Industries and Kohler round out the top five. All five have publicly discussed extended lead times through 2024-26 driven by simultaneous demand from data centres, industrial resilience upgrades, and hospital/critical-infrastructure spending. Caterpillar reported record backlogs on its Solar Turbines gas-turbine business in 2025; Cummins similarly on its Cummins Power Generation segment.

The natural-gas transition. Diesel gensets have been the default for decades because diesel is stable in storage and generators are proven. Natural-gas gensets have gained share as environmental and permitting concerns around diesel storage tightened. Gas has three advantages (lower particulate emissions, lower per-kWh CO₂, no on-site fuel storage requirement) and one disadvantage (dependence on a live gas pipeline, which stays no more resilient than the electric grid the generator is backing up). For "pure standby" duty, diesel remains common. For "long-run continuous during grid absence" duty (which is what behind-the-meter power is), gas dominates.
L7Behind-the-meter power

How are hyperscalers bypassing the grid, one campus at a time?

The behind-the-meter (BTM) power story is the biggest strategic development in the interconnect stack of the past two years. When grid interconnect timelines run four to seven years and hyperscalers want capacity in eighteen months, the arithmetic no longer works. The response has been to develop on-site generation at scale, sized to be the primary or majority power source; backup framing understates the role. Three technology classes are being deployed.

Gas turbines

The most mature option. GE Vernova's aeroderivative LM6000 (46-52 MW), LM2500 family (LM2500+ ~28 MW, LM2500+G4 ~33-34 MW), and stationary 7HA-class (~350 MW); Siemens' SGT-A65 and larger frames; Mitsubishi Heavy's H-class. Aeroderivatives can start in minutes and load-follow, which matches data centre demand well. Combined-cycle configurations (adding a steam turbine that runs off exhaust heat) push efficiency to 60%+. Multiple hyperscale campuses in Texas, Georgia and Virginia have announced or built dedicated gas-turbine plants sized at hundreds of MW.

Fuel cells

Bloom Energy has become the most visible BTM fuel-cell vendor for data centres, with multi-hundred-MW deployments announced with hyperscalers including Equinix and various colocation operators. Bloom's solid-oxide fuel cells run on natural gas (or hydrogen where available), operate at high efficiency (~60% electrical, higher with cogeneration), and can be sited compactly on the data centre campus. FuelCell Energy uses molten-carbonate technology in a similar deployment model. Fuel cells have significant advantages (no combustion emissions, quiet, modular) and one significant disadvantage (installed cost per kW is higher than gas turbines at scale).

Small modular reactors (SMR)

The most-discussed and least-deployed category. As of 2026, no commercial SMR is operating in the United States. Multiple pilot projects are in development: Amazon's investment in and PPA with X-Energy (four-unit HTGR site in Washington), Google's MOU with Kairos Power for a fluoride-salt-cooled unit, Meta's exploration of nuclear PPAs, and various utility-scale SMR programmes (NuScale in Idaho with UAMPS, formerly, since restructured; GE Hitachi BWRX-300 at OPG in Ontario; Rolls-Royce SMR programme in the UK). First commercial SMR power to a hyperscale customer is unlikely before 2029-31 at the earliest. But the announcements matter now because they signal the direction of travel: hyperscale customers are willing to commit to novel generation technologies if it decouples them from grid timelines.

Reported behind-the-meter commitments by hyperscale customers
Announced or contracted capacity, MW, by technology, cumulative through mid-2026
Compiled from hyperscaler press releases, utility announcements and trade press (S&P Global, Data Center Dynamics, Bloomberg). Includes existing nuclear PPAs (Amazon-Talen, Constellation-Meta, Microsoft-Three Mile Island), announced gas-turbine plants, Bloom fuel cell contracts, and SMR MOUs/PPAs. Uncontracted MOUs weighted lower than firm contracts.
Behind-the-meter power has moved past niche status to become the strategy every hyperscaler now runs in parallel with grid interconnection, and that shift is why gas-turbine, fuel-cell and SMR order books have simultaneously expanded to record levels.The BTM thesis
$Market size, TAM, and Profit pools

Sizing the interconnect market

The published range

Global electrical grid equipment markets are large and well-documented. Total global T&D equipment revenue is roughly $150-200B annually. Large power transformers are approximately $30-40B of that. MV switchgear runs $40-55B. HV/MV cables $50-70B (including submarine cables, which are outside the data centre scope). Gensets and standby generation $20-25B. Fuel cells for stationary power ~$3-5B. Wrapping around all of it, global copper markets are roughly $250-300B in mine output value at 2024-25 prices.

The AI data centre slice of these markets is smaller but growing fast. Combining rack-level content per MW with hyperscale build rates yields a bottom-up estimate.

Bottom-up TAM for AI data centre interconnect

Rack-level and campus-level interconnect content per MW of IT load, indicative:

  • Large power transformer (50-150 MVA class): ~$30-45k per MW at OEM prices, plus installation.
  • MV switchgear (substation + distribution): ~$25-35k per MW.
  • MV cables (site-scale copper/XLPE): ~$20-30k per MW depending on campus layout.
  • Backup generation (gensets sized for full IT load at N+1): ~$40-60k per MW installed.
  • Behind-the-meter primary generation (where deployed): $800-1,500k per MW installed for gas turbine, $2,000-3,500k per MW for fuel cell, $6,000-12,000k per MW for SMR (illustrative future).
  • Copper and misc conductor: ~$25-35k per MW at 2025 prices.

Excluding the behind-the-meter primary generation category (where deployment stays absent), interconnect content averages roughly $150-200k per MW of IT load for a hyperscale campus. Including primary-generation BTM (where applicable), the figure can climb toward $1M+ per MW.

Interconnect content per MW of AI IT load
Waterfall build, USD thousands per MW, hyperscale campus without behind-the-meter primary generation
Author's build. Ranges vary widely by capacity class, voltage class, redundancy design and OEM. Values shown are midpoints of stated ranges. Does not include BTM primary generation, which typically comes on top when deployed.

Applying that content per MW to the ~7-9 GW of AI IT-load additions modelled in Part II (and reused in Part III) gives a 2026 TAM of roughly $1.2-1.7B in narrow interconnect equipment, or $12-18B including construction, engineering and servicesIncluding BTM primary generation lifts the ceiling substantially: by 2030, if 20-30% of new AI capacity is BTM-primary (not grid-primary), the total could exceed $60B. Full workings in Annex §A1.

Bottom-up TAM: AI data centre interconnect
USD billions, 2026-2030E, base case, includes BTM at rising share of new AI capacity
Author's model. Assumes AI IT-load additions of 8 GW in 2026 rising to 15 GW by 2030 (from Part II), interconnect content per MW of ~$180k, and BTM primary generation share of new capacity rising from 5% (2026) to 25% (2030). Cross-checked against announced hyperscale power deals through mid-2026.

Profit pools

The profit-pool inversion that Parts II and III described (smaller components hold better margin) plays out somewhat differently in interconnect. The categorisation is more about scarcity rent than about qualification barriers.

  • GOES (~25-35%): materials-industry margins, protected by concentrated supply and long expansion lead times. The best-defended layer.
  • Large power transformers (~15-22%): heavy-industrial margins, currently benefiting from scarcity pricing in the current cycle. Sustainable at elevated levels as long as backlogs persist.
  • MV switchgear (~18-25%): better than transformers because product diversity is higher and switching-mechanism IP holds. Digital and clean-gas products deliver higher margins than baseline.
  • MV cables (~10-15%): commodity-plus economics; margin comes from scale and specialty products (submarine, HVDC).
  • Copper (fluctuating with commodity): mining margins vary widely by ore body and cycle; smelter margins compressed while fabrication margins land in the low-teens.
  • Backup gensets (~15-20%): healthy through the current lead-time cycle, would compress in a normal market.
  • Fuel cells (~5-15% and improving): Bloom Energy and peers still scaling into profitability; margin trajectory positive but modest.
  • SMR (loss-making): pre-commercial; all margin discussion is speculative until units are operating.
M&ACapital · Consolidation

The consolidation is done, the operations phase is beginning

The strategic map of interconnect equipment consolidated over 2018-2024 through a series of large transactions. The big pieces have moved. What remains is bolt-on M&A, capacity expansion capex, and operational execution.

Transaction / eventYearImpact
Hitachi acquires ABB Power Grids2020 ($11B)Created Hitachi Energy as the largest global player in T&D equipment. Combined ABB's Western customer relationships with Hitachi's manufacturing depth. Backlog and order book have expanded since.
Siemens Energy carve-out2020Separated grid, gas turbine and offshore wind businesses from Siemens AG. Focused entity, publicly listed, dedicated capex programme. Combined with Siemens Gamesa Renewable Energy since.
GE Vernova spin2024General Electric split into GE Aerospace, GE Vernova (energy) and GE HealthCare. Vernova as a standalone entity has been aggressive on grid capex and backlog growth.
Eaton acquisitions2024-26Eaton has been a serial data-centre acquirer per press releases: Fibrebond ($1.4B, closed April 2025), Resilient Power (2024), Ultra PCS ($1.55B, closed Jan 2026), Royal Power (2025), Boyd Thermal ($9.5B, closed March 2026). Grid-to-chip integration is Eaton's positioning theme; the acquisitions have executed it.
Constellation restarts TMI2024 (announced)Constellation Energy signed a 20-year PPA with Microsoft to restart Three Mile Island Unit 1 (renamed Crane Clean Energy Center), targeting 2028 return-to-service. First commercial nuclear restart driven by data centre demand.
Amazon. Talen (Susquehanna)2024Amazon acquired data centre campus adjacent to Talen's Susquehanna nuclear plant with rights to draw up to 960 MW under the original 2024 deal (subsequently expanded via a June 2025 PPA covering up to 1.92 GW over 17 years) behind-the-meter. FERC review continues to complicate the structure but the deal set the template for nuclear-adjacent siting.
Bloom Energy scaling2024-26Multiple hyperscale contracts announced, cumulative order book growing quarter over quarter. Bloom is transitioning from "specialty vendor" to "primary generation supplier" for BTM data centre power.

What is still on the board

  • Regional US LPT manufacturers (Delta Star, Virginia Transformer, Pennsylvania Transformer) as consolidation targets for larger OEMs looking to expand domestic capacity. Small revenue, high strategic value under CHIPS Act and DOE Loan Programs Office funding.
  • SMR developers as investment targets from hyperscalers and industrial groups. Post-restructuring NuScale, private Kairos and Oklo, Rolls-Royce SMR: equity valuations vary widely by regulatory progress.
  • Cable manufacturers outside the top five (Southwire in the US, regional European specialists) as consolidation targets for Prysmian/Nexans/NKT. Data centre demand has raised the strategic value of MV cable capacity.
  • Fuel cell and specialty gas turbine developers as venture and strategic capital continues to flow into BTM power.
TECHDisruption watch list

What could change the structure of this market

VectorWhat it isWhoImpact
Solid-state transformers (SST)Medium-voltage AC-DC-AC conversion using SiC/GaN power electronics in place of a line-frequency transformer coreHitachi Energy, Siemens Energy, ABB, university and DOE programmes; adjacent to Part II wide-bandgap suppliersIf commercial-scale SSTs deploy, they erode LPT volume at the sidecar level and pull medium-voltage SiC demand forward. Timeline uncertain; production units at hyperscale voltage classes remain limited.
Amorphous-core LPTsAmorphous metal (Metglas) replaces GOES in transformer cores, cutting no-load losses ~70%Hitachi Metals / Proterial; regional LPT builders; Chinese amorphous producersBounded impact at LPT scale because of handling difficulty. Would relieve GOES pressure at the distribution transformer scale where the substitution is already commercial.
Digital / asset-managed transformersSensor packages, oil DGA monitoring, thermal telemetry, integrated with cloud analyticsHitachi Energy, Siemens Energy, ABB, third-party analytics vendorsAdds a service tail to transformer sales. Small revenue today, high margin, structurally growing. Changes the transformer OEM economics toward a razor/blade model.
SF6-free MV switchgearClean-air, dry-air, or fluoronitrile alternatives to SF6 for insulation and interruptionHitachi Energy (EconiQ), Siemens (Blue GIS), GE Vernova (g3), ABBRegulatory-driven displacement of SF6 accelerates 2026-30. Higher unit prices, similar performance. Resets MV switchgear procurement decisions.
Behind-the-meter SMRSmall modular reactors sited on hyperscale campuses, running BTMNuScale, X-Energy, Kairos, Oklo, GE Hitachi BWRX-300, Rolls-Royce SMR2029-32 for first commercial units. If it works, redraws the data centre siting map and substantially reduces grid-interconnect dependency for the biggest customers.
HVDC interconnectorsHigh-voltage DC point-to-point transmission between generation and load centres, using SiC/IGBT valvesHitachi Energy, Siemens Energy, GE Vernova, NKT/Prysmian cablesEnables long-distance transmission from renewable-rich or nuclear regions to data centre load centres. Cable and valve-hall lead times are the constraint.
Distributed / meshed campusesInstead of one large substation feeding multiple buildings, distributed medium-voltage feeds from multiple grid pointsUtilities, hyperscaler engineering teamsReduces single-point-of-failure risk and can improve interconnect timeline by tapping smaller available capacity at multiple grid nodes. Adds complexity, higher unit cost.
Aluminium and Cu-Al hybrid busbarsSubstitute aluminium for copper where mass allows, reducing copper intensity per MWFabricators (Wieland, KME), rack integratorsBounded substitution at MV cable and busbar level. Does not touch the transformer winding or the smallest cross-section copper.
Superconducting MV cablesCryogenic high-temperature superconductor cables moving an order of magnitude more current per cross-sectionNKT, SuperPower, research consortiaCommercial pilots exist (LIPA in New York); economics do not yet close for standard data centre applications. Watch, don't underwrite.
RISKTrade-offs, Policy, and Winners

Trade-offs, and the argument against

The permitting and policy layer

Grid interconnect spans beyond an equipment problem. Federal, state and local permitting timelines for new transmission lines, substations and generation facilities have expanded over the past two decades. NEPA reviews, state siting boards, community consent, environmental impact assessments, transmission cost allocation between ratepayers and load: each is a genuine process with legitimate constituencies, and the cumulative timeline for a major new interconnection can consume years. The Inflation Reduction Act and various federal permitting reform proposals have made incremental changes, but nothing fundamental has shifted. Interconnect is now as much a policy problem as an equipment problem, and the equipment problem is severe enough on its own.

The commodity risk

Copper prices could correct if global demand normalises faster than expected, if mining supply comes online faster, or if AI capex slows materially. GOES supply could ease if Chinese exports increase (currently limited by domestic demand and provenance rules). Interconnect vendors have benefited enormously from scarcity pricing over the past three years; some of that will normalise as capacity expansions land in 2027-28.

Who wins, who is pressured

  • Winners: the three global LPT majors (Hitachi Energy, Siemens Energy, GE Vernova) through the current cycle, with margins holding as long as backlogs persist; MV cable majors (Prysmian, Nexans, NKT) similarly; the top switchgear vendors as SF6 alternatives expand ASPs; Bloom Energy and gas turbine OEMs on BTM demand; GOES producers on durable material scarcity; integrated grid-to-chip platforms (Eaton, Schneider, Vertiv) on the bundling thesis.
  • Under pressure: hyperscalers whose expansion depends on grid interconnect timelines they cannot control (some Meta, Microsoft, Amazon deployments have visibly slipped); utility-scale customers competing with hyperscalers for the same LPTs and switchgear; smaller regional LPT builders whose capacity is being locked up by hyperscale contracts and priced out for utility replacement customers.
  • The dominant risk: a slowdown in AI capex would relieve the equipment scarcity, normalise lead times, and compress the margins that OEMs have been enjoying. The equipment vendors are levered to hyperscaler capex in the same way that Parts II and III described the semiconductor and cooling vendors being levered.

Ten leading indicators to watch

  1. LPT backlog-to-revenue ratios at Hitachi Energy, Siemens Energy and GE Vernova. The sector's health in one number.
  2. GOES capacity announcements from Japanese and Korean producers. The materials layer's leading indicator.
  3. US ISO interconnect queue timelines (PJM, ERCOT, MISO, CAISO). When these compress, the BTM strategy's economic case softens.
  4. Announced hyperscale BTM primary-generation deals. The pace of the workaround.
  5. SMR commercial operating date announcements. Especially X-Energy, Kairos, GE Hitachi BWRX-300, NuScale.
  6. Federal permitting reform legislation. Would compress interconnect timelines if it lands.
  7. Bloom Energy quarterly bookings. The BTM fuel-cell leading indicator.
  8. Copper spot price and LME inventories. The commodity temperature check.
  9. Any regulatory ruling on Amazon. Talen or similar co-located nuclear deals. Sets precedent for BTM nuclear siting.
  10. Announced hyperscaler capex slowdowns or accelerations. The demand-side signal.
BOTTOMThis layer

Closing

The interconnect stack is the layer of AI infrastructure most exposed to physical grid constraints and policy timelines, and the layer where the industry response has been to route around the constraint through behind-the-meter power. That response is now visible in every hyperscaler's capacity plan. Gas turbines, fuel cells, and eventually SMR will take on some fraction of AI power demand that the grid cannot serve on the timeline hyperscalers need. The underlying equipment layers (LPTs, switchgear, cables, gensets) remain in shortage, and the materials layer beneath them (GOES, copper) is structurally tight. For operators, the message is that interconnect capacity is the constraint to plan around, and the planning horizon is now measured in years. For investors, the interconnect equipment vendors have been re-rating over the past three years and the multi-year backlogs suggest that re-rating has further to run.

This is Part IV of a six-part series. Across the earlier three parts (capacitor stack, wide-bandgap semiconductors, thermal management) and this one, the through-line has been consistent: the physical infrastructure of AI compute has become supply-constrained across every layer at once, in ways that most compute-side commentary underweights, and the profit pools are migrating in each layer toward the components where qualification, materials chokepoints or lead-time scarcity create durable pricing power. Interconnect is the layer where those dynamics land most heavily on the calendar. The next several years of AI infrastructure growth will be paced by grid connections, transformer factories and generator lead times.

ANNEXSources, Calculations, and Assumptions

Annex: how every derived number was built

Every figure in this piece is either published (traceable to a named source), derived (calculated from published inputs), or estimated (my judgement, labelled). This annex covers the latter two.

§A1. TAM model for AI data centre interconnect

Status: derived. Full workings below.

Content per MW inputs. LPT (50-150 MVA class): ~$30-45k per MW of IT load at OEM prices, based on published utility procurement data and hyperscale-scale unit pricing through 2025. Add ~30-50% for installation, testing and commissioning. MV switchgear: ~$25-35k per MW based on Schneider Electric, Eaton and ABB product-line pricing scaled to campus loading. MV cables: ~$20-30k per MW based on Prysmian/Nexans quotations for XLPE MV cable systems, scaled to typical campus layout of 5-10 km MV runs per 100 MW. Gensets (N+1 diesel at full load): ~$40-60k per MW installed based on Caterpillar/Cummins list pricing plus integration and fuel systems. Copper and misc: ~$25-35k per MW at 2025 copper spot around $9,500/tonne, at 30 tonnes per MW.

Total interconnect content per MW. Sum of the above: ~$140-210k per MW of IT load, midpoint ~$175k. Author's build; individual line items are estimates.

Volumes. AI IT-load additions per Part II model: ~7-9 GW in 2026 rising to ~14-18 GW by 2030. Independent cross-check against Kuo's VR200 shipment estimates and JLL/McKinsey capacity forecasts.

Narrow TAM (equipment only). 8 GW × $175k/MW = ~$1.4B of narrow interconnect equipment in 2026 per author's bottom-up model. Extending to 2030 at 15 GW × ~$180k/MW (nominal content stability) = ~$2.7B by 2030.

Wide TAM (including EPC, engineering, services). Applies a 8-10× multiplier to the narrow TAM for engineering, construction, installation and commissioning services. Author's assumption; based on utility grid capex ratios where equipment is typically 15-20% of total substation project cost. Gives ~$12-18B for 2026, ~$20-28B by 2030 excluding BTM.

Including BTM primary generation. Assumes BTM primary share of new AI capacity rises from ~5% in 2026 (~0.5 GW at ~$1.5M/MW gas turbine average) to ~25% by 2030 (~4 GW × ~$1.5M/MW blended average across gas, fuel cell, early SMR). Adds estimated ~$0.7B in 2026 rising to ~$6B by 2030 per author's model. Combined wide TAM including BTM: ~$13-19B for 2026 rising to ~$26-34B by 2030. Bull case with heavier SMR deployment and higher grid-constraint pressure could reach $45-65B by 2030. Sensitivities are dominated by (1) AI capacity growth rate, (2) BTM share assumption, (3) SMR commercial operating date.

§A2. GOES supply and share

Status: estimated. Global GOES production stays inconsistently published. Author's estimates: Nippon Steel + JFE ~30-40% combined (dominant in domain-refined grade); POSCO ~10-15%; Cogent (Tata) and ArcelorMittal ~15-20% combined; NLMK/DK ~5-10% (subject to sanction-related uncertainty); Chinese producers (Baosteel, TISCO, WISCO) ~25-30% combined (largely consumed domestically). Add small production from AK Steel (Cleveland-Cliffs) in the US, and Indian producers (SAIL). Figures directional only; consult Metal Bulletin and SteelOrbis for current data if precision is needed.

§A3. LPT lead time trajectory

Status: published across multiple sources, with ranges. Pre-pandemic US LPT lead times of 40-60 weeks are documented in DOE 2014 and 2017 supply-chain studies. Post-pandemic expansion to 120-150 weeks is documented in DOE 2022 and 2023 studies, plus EPRI, T&D World and utility engineering-firm surveys through 2025. Specific hyperscale-class units have been quoted at 200+ weeks by industry contacts through 2025-26; not independently verified.

§A4. Interconnect queue timelines

Status: published. Lawrence Berkeley National Laboratory's annual "Queued Up" report tracks US ISO interconnect queues. As of the 2024 edition (published 2025 with 2024 data), typical queue times for large generation projects run 3-5 years in most ISOs, with large-load interconnections (data centres) reporting similar or longer waits in PJM, ERCOT and MISO. Individual data centre operators have publicly cited 4-7 year timelines for specific sites.

§A5. Copper intensity per MW

Status: estimated ranges, cited in industry press. BHP, Wood Mackenzie, S&P Global Commodity Insights and IEA have each published estimates in the 30-65 tonnes per MW range for data centres, with wider variation for AI-optimised hyperscale (higher end). The 3-5× multiplier vs legacy enterprise is a widely cited industry rule of thumb; specific studies vary. Global copper demand estimates and deficit forecasts through 2030 are from the same source cohort.

§A6. Behind-the-meter deal tracker

Status: compiled from press releases and trade press through mid-2026. Major announced or contracted deals include: Amazon. Talen (Susquehanna, ~960 MW capacity rights), Microsoft. Constellation (Three Mile Island Unit 1 restart, ~835 MW targeting 2028), Meta. Constellation (Illinois nuclear PPA, ~1,100 MW), Amazon. X-Energy (Washington HTGR site, 4 units × 320 MW each), Google. Kairos (fluoride-salt SMR MOU, ~500 MW), plus numerous smaller gas-turbine and Bloom Energy deals. Deal sizes and timelines subject to regulatory approval and construction risk; figures are announced capacity.

§A7. Other published figures used

  • Hitachi Energy backlog: reported multi-year highs through 2025; specific backlog values from company disclosures.
  • Siemens Energy grid capex programme: €4.5B+ announced through 2027, various company disclosures.
  • Eaton acquisitions: Fibrebond $1.4B, Ultra PCS $1.55B, Boyd Thermal $9.5B, others undisclosed; Eaton press releases and Reuters.
  • SF6 GWP: ~23,500 relative to CO₂, atmospheric lifetime 3,200 years; IPCC AR6 (2021).
  • Bloom Energy hyperscale deployments: multiple announcements through 2024-26; Bloom Energy press releases and trade press.
  • Copper spot price: ~$9,500/tonne baseline 2025, ~$10,500-11,500/tonne range through 2026; LME.
A caution on this sector's data. Grid equipment markets are less transparently reported than semiconductor or capacitor markets. Company disclosures are heavily aggregated; trade press is fragmented; regulatory filings from utilities are voluminous but hard to aggregate. Where I have quoted numbers, I have flagged the source. Where I have estimated, I have said so. This annex is a starting map for diligence.
SERIESRelated in the AI Power Chain

The complete series

This is Part IV of the AI Power Chain series. The six parts cover the physical infrastructure of AI compute, layer by layer, from the medium-voltage utility bus to the 0.8V transistor gate. Each part has a technical companion that walks through the underlying physics.

For readers who want the physics behind this piece (transformer efficiency, GOES manufacturing, SF6 alternatives, XLPE cables, aeroderivative turbines, SOFC fuel cells, four SMR families), see the technical companion: The Interconnect Stack: Technical Companion.

The Capacitor Stack (Part I) covers hybrid supercapacitors, EDLCs, MLCCs, silicon capacitors and Al electrolytics. Technical companion: The Capacitor Stack: Technical Companion.

The Wide-Bandgap Stack (Part II) covers SiC and GaN power semiconductors after the substrate glut. Technical companion: The Wide-Bandgap Stack: Technical Companion.

The Thermal Stack (Part III) covers data centre liquid cooling from die to dry cooler. Technical companion: The Thermal Stack: Technical Companion.