ADI KUMAR · POWER & DIGITAL INFRASTRUCTUREAUGUST 2026 · V1 · ~45 MIN READ
The AI Power Chain · Part IV of VI
Market deep dive · Grid interconnect & interconnect equipment

The Interconnect Stack: Transformers, Switchgear and the Grid Equipment That Gates the AI Buildout

Every gigawatt of AI capex assumes an interconnected grid connection with sufficient MV switchgear, a large power transformer and a set of medium-voltage cables to route the current. In 2026 that assumption no longer holds. LPT lead times have doubled since 2023, GOES supply is concentrated in three producers, US interconnect queues run four years, and hyperscalers have started building their own generation to escape the wait. A layer-by-layer analysis from grain-oriented electrical steel to grid queue reform.

Executive summary. Nine findings.
  1. Grid interconnect is now the binding constraint on AI, not compute, not cooling, not chips. New large-load interconnect timelines in PJM, ERCOT, MISO and CAISO commonly run 4–7 years from application to energisation. Every hyperscaler ordering GW-class capacity in 2026 is planning around a wait that could stretch into the next decade.
  2. Large power transformer lead times have doubled since 2023. A 138/33 kV or 230/34.5 kV substation-class LPT that took 50–60 weeks pre-pandemic now takes 120–150+ weeks in North America. Global order books at Hitachi Energy, Siemens Energy and GE Vernova have been reported past record highs, with the three sitting on multi-year backlogs.
  3. GOES (grain-oriented electrical steel) is the underlying materials chokepoint. Roughly five producers globally (JFE Steel, Nippon Steel, POSCO's spinoff, ArcelorMittal / Cogent, NLMK), with China's Baosteel and TISCO adding capacity. GOES is the transformer core material and its manufacturing takes 12–18 months to expand. It is the Kuraray of the interconnect stack.
  4. Behind-the-meter power has moved from workaround to strategy. Amazon at Susquehanna, Meta at Clinton (Constellation), Microsoft at Three Mile Island, Google's Kairos SMR MOU, plus dozens of gas-turbine and Bloom Energy fuel cell deals. What used to be "on-site generation for redundancy" is now "on-site generation because we cannot wait for the grid".
  5. Copper demand from AI adds a materials layer stress that most models miss. Hyperscale racks use roughly 3–5× the copper per MW of a legacy enterprise data centre. On top of EV and renewables demand, AI could add 1–2 million tonnes/year of incremental copper consumption by 2030, into a supply base already forecasting deficits.
  6. The M&A window for interconnect assets has closed. Hitachi bought ABB Power Grids in 2020. GE broke out Vernova in 2024. Cameron International, Emerson process, PGE, Sensata: the big consolidations are done. What remains is bolt-ons and JVs, not platform deals.
  7. Digital and asset-managed transformers are the emerging profit lever. Adding sensor packages, oil-quality monitoring and thermal telemetry lets OEMs sell a service tail alongside the box. Hitachi Energy, Siemens Energy and Mitsubishi Electric all now have dedicated digital-transformer product lines. Software attach is small revenue today, high-margin, and structurally growing.
  8. Chinese equipment is qualifying into the AI supply chain for cables and medium-voltage switchgear, less so for large power transformers. TBEA and Baoding Tianwei have made international sales, but hyperscalers' provenance rules and utility qualification cycles are the real barriers.
  9. Bottom-up TAM. AI data centre interconnect capex sits at roughly $12–18B in 2026 (~$150–200k per MW of IT load, on ~8GW of new build) rising to $45–65B by 2030 as the buildout scales. Transformers, switchgear and cables dominate; behind-the-meter generation is the emerging category.
GWStage 0 · The thesis
The AI Power Chain · six essays, one physical arc

The series walks a single physical path. It begins at the medium-voltage utility bus at the site fence, steps down through the substation and switchgear, arrives at the datacenter rack where 800V DC is stabilised by the capacitor stack, is converted by silicon-carbide switches to 48V, is distributed across the rack by copper busbars and whips, is stepped down again by multi-phase controllers on the accelerator board to 0.8V, and finally routed through the on-package power delivery network to a transistor gate drawing over 2,000 amperes. Waste heat from every conversion stage is removed by the thermal stack. The whole thing is packaged inside a factory-modular building because there aren't enough electricians to build it stick-frame. Six essays. One 800V → 0.8V staircase.

  1. Part I. The Capacitor Stack — 800VDC at the rack
  2. Part II. The Wide-Bandgap Stack — SiC and GaN conversion
  3. Part III. The Thermal Stack — removing the waste heat
  4. Part IV. The Interconnect Stack — busbars and whips (you are here)
  5. Part V. The On-Package Delivery Stack — 48V to 0.8V
  6. Part VI. The Modular Datacenter Stack — how the building gets built
$150k+
Estimated interconnect capex per MW of AI IT load, 2026 base
~3–5×
Copper per MW in a hyperscale AI rack vs a legacy enterprise data centre
Interconnect lead time expansion, by equipment class
Reported delivery lead times, weeks, 2019 vs 2026, indicative
Compiled from vendor guidance, EPRI briefings, DOE Loan Programs Office reports, and utility engineering-firm surveys through mid-2026. Ranges are wide because lead time depends on capacity class, voltage, customer priority and manufacturer relationship. The direction and magnitude of the change are consistent across sources.

The mismatch between AI capex velocity and interconnect physics has driven the behind-the-meter generation wave, the acceleration of small modular reactor pilots, hyperscaler direct multi-year procurement contracts with transformer OEMs, and a redrawing of the map of where data centres can actually be built. The utility-equipment supply chain, which had been low-growth and stable for two decades, is now one of the two or three most strategically constrained resources in AI infrastructure.

MAPThe framework · Eight layers, one grid path

The interconnect value chain, layer by layer

The capacitor stack divided by timescale. The wide-bandgap stack divided by process step. The thermal stack divided by heat-path position. The interconnect stack divides by voltage class and physical position between utility and rack. Each layer has a different competitive structure, a different concentration profile, and a different lead-time exposure. The market map below names the players at every layer. Two things stand out before reading it: the Japanese and Korean depth in materials and heavy equipment (GOES, LPT, HV cables) and the fact that the same four or five industrial groups (Hitachi Energy, Siemens Energy, Schneider Electric, ABB, Eaton) appear at multiple layers. Interconnect is a heavily integrated business, and it has been that way for decades.

The AI data centre interconnect market map
Named players by layer · leaders highlighted · August 2026
L1Grain-oriented electrical steel (GOES)Silicon-steel laminations for transformer cores · roughly 5 global producers
Cogent (Tata) UK/IN
ArcelorMittal FR
POSCO KR
NLMK / DK RU/DK
Baosteel CN
TISCO / Taiyuan CN
AK Steel (Cleveland-Cliffs) US
Wuhan Iron & Steel CN
Steel Authority of India IN
L2Large power transformers (LPT)≥100 MVA units for substations · concentrated in three global majors + regional players
Hitachi Energy (ex-ABB) CH/JP
Siemens Energy DE
GE Vernova US
Hyundai Electric KR
HHI (LS Group) KR
Toshiba Energy Systems JP
WEG BR
Prolec-GE (Xignux) MX
SGB-SMIT DE
TBEA CN
Baoding Tianwei CN
Wanshiba (WEG-China) CN
CG Power / Bharat Heavy IN
Delta Star US
Virginia Transformer US
ERMCO / Pennsylvania Transformer US
L3MV / LV switchgearAir-insulated, gas-insulated (SF6), vacuum, dry-air · switchgear for substation and distribution
Schneider Electric FR
ABB CH
Eaton US/IE
Siemens DE
Hitachi Energy CH/JP
Powell Industries US
Legrand (industrial) FR
Alstom Grid (ex-GE) FR
LS Electric KR
Hyundai Electric KR
CHINT · Delixi CN
nVent (Erico / Hoffman) US/IE
Vertiv (integrated) US
Rittal DE
L4MV / HV cablesXLPE-insulated MV cables · often kilometres per campus · four global majors + Chinese/Korean scale
Prysmian IT
Nexans FR
NKT DK
LS Cable & System KR
Southwire US
General Cable (Prysmian) US
Hengtong Group CN
ZTT (Jiangsu Zhongtian) CN
Far East Cable CN
Elka (Cable Coop) PL
L5Copper & conductor materialsMine · smelter · rod & wire · fabricated busbar
Freeport-McMoRan US
Southern Copper (Grupo México) PE/MX
BHP · Rio Tinto AU/UK
Glencore CH
Codelco CL · state
Zijin Mining CN
Aurubis DE · smelter
KME IT/DE · fab
Wieland Group DE · fab
Southwire US · fab
Sterlite / Vedanta IN
L6Backup generation · gensetsDiesel and natural-gas standby · years-long lead times · integrated with fuel and controls
Caterpillar US
Cummins US
Rolls-Royce mtu DE/UK
Kohler US
Generac US · industrial
MAN Energy Solutions DE
Vertiv (Liebert) US · integration
Eaton (Cyclonaire/Fibrebond) US · packaging
L7Behind-the-meter powerGas turbines · fuel cells · SMR (emerging) · alternative sources when grid queues bite
Bloom Energy US · SOFC
GE Vernova (LM6000/LM2500) US · gas turbine
Solar Turbines (Caterpillar) US
Siemens Energy (SGT) DE
FuelCell Energy US · MCFC
SFC Energy DE
NuScale US · SMR
X-Energy US · SMR
Kairos Power US · SMR
Oklo US · SMR
GE Hitachi (BWRX-300) US/JP · SMR
Rolls-Royce SMR UK
L8Grid connection · regulated utilityNot a commercial market · the constraint everything else is trying to route around
PJM Interconnection US · MW East
ERCOT US · Texas
MISO US · Midwest
CAISO US · California
ENTSO-E TSOs EU
National Grid (UK ESO) UK
TenneT · 50Hertz DE
Dominion · AEP · Duke US utilities
PG&E · SCE US · CA
Berkshire Hathaway Energy US
United StatesEuropeJapanChinaKoreaIndiaShaded tiles = category leaders
How to read this map. The shares and lead times quoted throughout this piece are approximate and drawn from public research of differing vintages and scopes. Treat them as positional, not precise. Two structural features stand out. First, the same handful of Western industrials appear at three or more layers each: Hitachi Energy, Siemens Energy, GE Vernova, Schneider Electric, Eaton, ABB, Mitsubishi Electric. Vertical integration across the transformer / switchgear / cable path is the norm, and it has been for decades. Second, the geography of concentration matters: large power transformers are majority Asian-manufactured (Japanese, Korean, plus rising Chinese and Indian), GOES is majority Japanese, and MV cables are split between three European giants and Asia. The North American production base is thin and expanding slowly.
L1Grain-oriented electrical steel