Leak-detection topology model
An author-built engineering scenario model. Every count, cable metre, controller, endpoint and cost figure is derived from four inputs and adjustable assumptions. Not a vendor design guide or industry-standard bill of materials.
Inputs
Advanced · geometry and unit costs
Coverage density
Cable distribution
Detection topology
| Layer | Cable m | Spots | Controllers | CDU telemetry |
|---|---|---|---|---|
| Facility / perimeter | 3,820 | 65 | 12 | — |
| Row / pod | 14,220 | 237 | 79 | — |
| Rack | 3,780 | 945 | via pod | — |
| CDU (physical + telemetry) | — | 198 | via pod | 99 |
| Total | 21,820 | 1,445 | 91 | 99 |
Cost breakdown
| Line | Count | $/each | Subtotal |
|---|---|---|---|
| Sensing cable | 21,820 m | $8 | $175k |
| Physical detection points | 1,445 | $180 | $260k |
| Pod controllers / hubs | 79 | $3,500 | $277k |
| Master locator panels | 12 | $8,000 | $96k |
| CDU telemetry endpoints | 99 | $400 | $40k |
| Integration gateways | 14 | $6,000 | $84k |
| Dielectric overlay | off | — | — |
| Hardware subtotal | — | — | $931k |
| Installation + field integration | at 35% of hardware | $326k | |
| Illustrative installed cost | — | — | $1.26M |
Detection ≠ localisation ≠ diagnosis ≠ response
Sensing cable, spot sensors, dielectric probes. Any layer can answer this. The bar is low.
Addressable cable, pod-level controllers, master locator panels. Only some architectures provide this.
Combining spot, cable, and CDU telemetry to distinguish a QD leak from a manifold pinhole. Software layer, not hardware.
Hardwired dry-contact to CDU solenoid, BMS alarm, isolation playbook. The value migrates here.
Four-scenario sensitivity
| Scenario | Rack density | Tier | Racks | Cable m | Endpoints | $/kW IT | Installed cost |
|---|---|---|---|---|---|---|---|
| Minimum | 60 kW | 1 | 1,417 | 4,605 | 363 | $6.2 | $528k |
| Reference | 90 kW | 2 | 945 | 21,820 | 1,544 | $14.8 | $1.26M |
| High density | 120 kW | 2 | 709 | 16,987 | 1,179 | $11.2 | $954k |
| High coverage | 90 kW | 3 | 945 | 26,870 | 1,623 | $20.0 | $1.70M |
Method
Everything derives from four primary inputs: gross MW, IT load factor, kW/rack, racks/pod. Everything else is either a coverage assumption you can override, or a unit cost you can override.
Rack count = ceil(IT MW × 1000 / kW per rack). Pod count = ceil(rack count / racks per pod). CDU count in row-based mode = ceil(pod count × CDUs per pod); in-rack mode = rack count.
Hall footprint is derived from gross facility area per rack (default 90 m², editable in Advanced) times rack count. Total footprint is split across multiple halls above 50 MW IT (one hall per 50 MW IT), so large campuses aggregate wall length across buildings rather than model an implausibly large single rectangle. Each hall is a rectangle with aspect ratio L:W (default 2:1, editable). Perimeter per hall = 2(L + W) where W = √(area / aspect) and L = aspect × W. Facility cable = aggregate perimeter × cable density (default 2.0 m of sensing cable per m of wall, includes multiple parallel runs along perimeter, plant walls and cold-aisle boundaries) + chilled-water riser runs.
Pod cable = 180 m × pod count in Tier 2 (0 m in Tier 1, 220 m in Tier 3). Rack cable = 4 m × rack count in Tier 2 (0 in Tier 1, 6 m in Tier 3).
Tier 3 adds a pod hub redundancy multiplier and optional dielectric overlay. Tier 1 strips pod and rack cable and rack spots entirely (perimeter and CDU only). Integration gateways scale at approximately 1 per 6 pods. Master locator panels scale at approximately 1 per 7 pods.
Unit costs are hardware only. The installation + integration factor is applied on top and is highly site-dependent (new build vs retrofit, cable routing, commissioning, contractor labour, geography).
Every value below the four primary inputs is an editable illustrative assumption. Change any of them to model your own scenario. Source discussion and named vendors in the leak-detection deep-dive.
DTC cooling · capex, opex + TCO calculator
If this leak-detection tool is telling you what the sensor and control layer costs, the DTC cooling calculator tells you what the underlying cooling architecture costs. Six architectural inputs, capex waterfall from the Fig C15 anchor, year-1 opex, 7-year TCO, payback engine, sensitivity matrix and scenario-sharing links. Same reader path.
Data Centre Cooling · a double-click on Direct-to-Chip
The parent architecture essay for both this leak-detection deep-dive and the DTC calculator. Nine-layer physical stack from GPU die and TIM through cold plate, QDs, manifold and CDU out to the facility loop. CDU as testable control-point proposition. Consolidation race (Ecolab-CoolIT, Schneider-Motivair, Eaton-Boyd, Vertiv-STL/PurgeRite). Investor decision map by profile.