Built for VP-level infrastructure architects. The four gates below cover thermal inertia buffer, rack density, PUE sensitivity, and regulatory classification. Together they determine whether a facility falls inside the commercial-DDC envelope, requires a hybrid DDC-plus-industrial-PLC split, or warrants a full mission-critical PLC control plane. Enter the facility parameters below for a scored recommendation.
Gate thresholds grounded in the reference architecture in The Industrial Building Management System. Author-defined scenario boundaries; a specific facility may fall outside these ranges. The tool structures the decision; the capex estimate below is an indicative scenario range for structuring the budget conversation, well short of a procurement quote.
Facility inputs
Pick the closest band for each gate. All four influence the recommendation.
Time without active cooling before server thermal throttling or trip.
Peak kilowatts per rack at the critical compute hall.
Dollar impact of a 0.01 PUE improvement across the facility, annual basis.
The strictest regulatory regime applicable to the facility.
Drives the controlled-point count estimate used in the capex card.
Recommendation
Recomputes on every input change. Score bands: 0-30 commercial DDC envelope; 31-60 hybrid architecture; 61-100 full mission-critical PLC control plane.
Hybrid architecture
Composite score 42 out of 100. Commercial DDC on general building loads, industrial PLC on the critical plant.
Thermal inertia
15 / 30
Rack density
12 / 25
PUE sensitivity
10 / 20
Regulatory class
0 / 25
Why this recommendation.
Fill in the facility inputs on the left; the rationale updates automatically.
Capex delta and SI readiness
Indicative scenario range: moving from a commercial DDC baseline to the recommended architecture. Author-estimated ranges drawn from publicly discussed SI pricing precedents; a specific facility would validate against vendor quotations before use.
Controlled-point count estimate
6,000 to 10,000
Mid-size facility estimate. Chiller plant, pumps, AHU, CRAH, CDU, electrical plant, and critical-equipment OEM controllers aggregated across the control architecture.
Baseline cost (commercial DDC)
$5.4 M to $9 M
At an author-estimated $800 to $1,200 per controlled point for BACnet/IP + MS/TP installations including field devices, panels, and engineering.
Recommended-band cost
$8.4 M to $14 M
Hybrid architecture: DDC on general loads at baseline rate; industrial PLC on the critical plant at an estimated $2,200 to $3,500 per point including hot-standby chassis, distributed I/O, PTP switches, and specialist SI engineering.
Capex delta vs DDC baseline
+$3.0 M to +$5.0 M
Range reflects the share of the controlled points that move to industrial-PLC content and the industrial-PLC per-point premium.
SI schedule buffer multiplier
1.3x to 1.6x
Applied to the mechanical-engineering commissioning schedule. The buffer absorbs IEC 61850 cross-testing, PTP alignment, hot-standby failover validation, and GOOSE message-mapping cycles before go-live.
OT engineering readiness
Hybrid team sufficient
A dedicated OT security engineer plus a specialist industrial SI covers the mid-score case; a captive OT engineering bench is normally required at the top of the scoring range.
Architecture band boundaries
Band
Composite score
What this looks like
What it does not look like
Commercial DDC envelope
0 to 30
BACnet backbone, mid-tier head-end supervisor, equipment DDCs on event-driven scheduling, trades-based support model.
No cross-interlock to electrical protection; no sub-100 ms recovery capability on critical plant.
Hybrid DDC + industrial PLC
31 to 60
DDC backbone covers general building loads; industrial PLC pair on the chiller plant and the critical electrical interlock; shared supervisor.
Not a full IEC 61850 cross-interlock across the entire facility; not every loop runs at 10-20 ms deterministic PID.
Full mission-critical PLC plane
61 to 100
Hot-standby PLC pair across mechanical and electrical domains; IEC 61850 GOOSE cross-interlock; IEEE 1588 PTP timing; dedicated OT engineering team.
Not justified for standard commercial buildings; carries capex premium and sustained OT labour cost.